Emergency Ambulatory Care ExpansionDaily Activity on Job Site - Mon November 17, 2008
![]() |
| cloudy |
![]() |
| 13ºC |
-Installing top soil for landscape
-Pour concrete ED-1103 pipe pad, NW stairs and entrance sidewalk
-Cleaning neighbours fence area
-Flooring upper link
-Installing millwork lower floor
-Personnel on site: 15 in total
Wales & Mcleland: 1 Superintendent, 1 Safety Officer, 1 Head Carpenter, 2 Laborers
Mott: 1
Landscape: 4
Towne: 3
Floors: 2
| Prep NW stairs | Prep sidewalk | Pour sidewalk | Pour NW stairs |
| Landscape topsoil | Landscape neighbours | Landscape topsoil | ED-1103 |