Daily Activity on Job Site - Wed November 19, 2008

sunny
 
13ºC

-Installing top soil for landscape & prep for tree planting
-Prep & cutting asphalt for old diesel fuel tank removal
-Cleaning neighbours fence area
-Flooring upper link
-Installing millwork lower floor

-Personnel on site: 16 in total

Wales & Mcleland: 1 Superintendent, 1 Safety Officer, 1 Head Carpenter, 3 Laborers
Landscape:4
CP: 1
Towne: 3 
floors:  2




Front entrance Front entrance Front entrance Parking lot
Parking lot Locate O2 line Locate O2 line Lower link