RMH
Emergency Ambulatory Care ExpansionDaily Activity on Job Site - Mon November 3, 2008
![]() |
| rain |
![]() |
| 10ºC |
-Installing top soil for landscape
-Cleaning lower link and existing hall way to main hospital
-Installing door hardware lower link
-Installing new door frame to staff room lower link
-Installing scaffold in elevator shaft to mount support beam
-Strip sidewalk from entrance
-Prep for paint outside beams
-Removing bus duct to T1 & from the old generator and prep to remove generator
-Personnel on site: 13 in total
Wales & Mcleland: 1 Superintendent, 1 Safety Officer, 1 Head Carpenter, 3 Laborers
Mott: 2
LDP: 1
Landscape: 4
| Staff door frame AC-0202 | Install elevator beam | Broken glass upper link | Strip sidewalk |
| Prep for painting | Landscape topsoil | Landscape topsoil | Landscape topsoil |