Emergency Ambulatory Care ExpansionDaily Activity on Job Site - Tue November 4, 2008
![]() |
| partial cloud |
![]() |
| 10ºC |
-Installing top soil for landscape
-Cleaning lower link and existing hall way to main hospital
-Installing door hardware lower link
-Installing new door frame to staff room lower link
-Installing support beam in elevator shaft
-Strip sidewalk from entrance
-Prep for paint outside beams
-Removing bus duct from the old generator and prep to remove generator
-Personnel on site: 16 in total
Wales & Mcleland: 1 Superintendent, 1 Safety Officer, 1 Head Carpenter, 4 Laborers
Mott: 2
LDP: 1
Town: 2
Landscape: 4
| Scope room AC-0094 | Landscape topsoil | Landscape topsoil | Landscape topsoil |
| Landscape topsoil | Entrance turnaround | Upper link | Elevator beam |