Daily Activity on Job Site - Wed November 5, 2008

partial cloud
 
7ºC

-Installing top soil for landscape 
-Installing new door frame to staff room lower link
-Install support beam in elevator shaft 
-Remove load shed for panel 'T' N/S elevator feeder
-Remove building alarms from the generator panel
-Install ceiling tiles upper link
-Chipping upper link floor to prep for flooring
-Remove old lino in existing hallway lower link
-Install lighting fixtures in stairwell and lower link

-Personnel on site: 14 in total

Wales & Mcleland: 1 Superintendent, 1 Safety Officer, 1 Head Carpenter, 3 Laborers
Mott: 3
Landscape:  5




Strip lino lower hallway Strip lino lower hallway Lower link lighting Strip upper link
Landscape topsoil Landscape topsoil Landscape topsoil Landscape topsoil