-Installing top soil for landscape
-Installing new door frame to staff room lower link
-Install support beam in elevator shaft
-Remove load shed for panel 'T' N/S elevator feeder
-Remove building alarms from the generator panel
-Install ceiling tiles upper link
-Chipping upper link floor to prep for flooring
-Remove old lino in existing hallway lower link
-Install lighting fixtures in stairwell and lower link
-Personnel on site: 14 in total
Wales & Mcleland: 1 Superintendent, 1 Safety Officer, 1 Head Carpenter, 3 Laborers
Mott: 3
Landscape: 5
| Strip lino lower hallway | Strip lino lower hallway | Lower link lighting | Strip upper link |
| Landscape topsoil | Landscape topsoil | Landscape topsoil | Landscape topsoil |