RMH
Emergency Ambulatory Care ExpansionDaily Activity on Job Site - Thu November 6, 2008
![]() |
| rain |
![]() |
| 7ºC |
-Installing top soil for landscape
-Installing new door frame to staff room lower link
-Remove schafolding elevator shaft
-Install ceiling tiles upper link
-Chipping upper link floor to prep for flooring
-Remove old lino in existing hallway lower link
-Install lighting fixtures in stairwell and lower link
-Install overhead paging speakers
-Personnel on site: 16 in total
Wales & Mcleland: 1 Superintendent, 1 Safety Officer, 1 Head Carpenter, 3 Laborers
Mott: 2
LDP: 1
CP: 1
DE: 3
Phoenix: 3
| Strip floor hallway | Door frame AC-0202 | Install speakers | Upper link |
| Elevator beam | upper elevator lobby | Upper link entrance | Schafolding fire escape |