Emergency Ambulatory Care ExpansionDaily Activity on Job Site - Fri November 7, 2008
![]() |
| rain |
![]() |
| 11ºC |
-Installing top soil for landscape
-Install ceiling tiles upper link
-Remove old lino in existing hallway lower link
-Install lighting fixtures lower link
-Repair 3/4" emt pipe to maintenance computer room
-Relocate compactor to temporary location West side on the loading bay
-Transfer & polish 1025 litres of diesel fuel from old generator tank to the new tanks
-Installing auto door opener oncology
-Personnel on site: 13 in total
Wales & Mcleland: 1 Superintendent, 1 Safety Officer, 1 Head Carpenter, 3 Laborers
Mott: 2
Landscape: 1
CP: 2
Canadian Fuel Oil Polishing: 2
| Compacter relocated | Polishing diesel fuel | Polishing diesel fuel | Polishing diesel fuel |
| Auto door oncology | Upper link tiles | Landscape topsoil | Landscape topsoil |