Daily Activity on Job Site - Fri November 7, 2008

rain
 
11ºC

-Installing top soil for landscape 
-Install ceiling tiles upper link
-Remove old lino in existing hallway lower link
-Install lighting fixtures lower link 
-Repair 3/4" emt pipe to maintenance computer room
-Relocate compactor to temporary location West side on the loading bay
-Transfer & polish 1025 litres of diesel fuel from old generator tank to the new tanks
-Installing auto door opener oncology

-Personnel on site: 13 in total

Wales & Mcleland: 1 Superintendent, 1 Safety Officer, 1 Head Carpenter, 3 Laborers
Mott: 2
Landscape:  1
CP: 2 
Canadian Fuel Oil Polishing:  2



Compacter relocated Polishing diesel fuel Polishing diesel fuel Polishing diesel fuel
Auto door oncology Upper link tiles Landscape topsoil Landscape topsoil