-Prep front of main bldg for landscape
-Installing T-Bar lower link and existing hall way to main hospital
-Cleaning lower link and existing hall way to main hospital
-Installing floor rear hall lower level
-Installing door hardware lower link
-Pour concrete elevator shaft floor
-Deliver curbs from MSA
-Place curbs around oxygen tank
-Transfer Conditional #1 to 750 KVA transformer from energy center
-Disconnect 600 KVA T1 & disconnect busduct from the existing Conditional distribution
-Turn off existing 25 KV Hydro feed from the Lougheed hyw
-All power to the existing building is now on the energy center, swing over is completed
-Personnel on site: 13 in total
Wales & Mcleland: 1 Superintendent, 1 Safety Officer, 1 Head Carpenter, 2 Laborers
Mott: 2
LDP: 3
Friesen: 3